Website Main content
Website Secondary navigation Council services

Current works

  • Completion of all current works is subject to weather conditions.

We will make every effort to minimise disruptions to traffic, parking and pedestrians during work times. We ask pedestrians and motorists to be aware of works and to adhere to any signage erected.

Batehaven, Beach Road

Single lane closure heading north on Beach Road between Corrigan Crescent and George Bass Drive to enable works on underground sewer lines. 

  • 6pm Friday 24 February to 6am Saturday 25 February
  • 6pm Sunday 26 February to 6am Monday 27 February 

Traffic control will be in place.

Contact: Platinum Traffic Services

Phone: 02 4474 1000

Batehaven, Corrigans Reserve

Installing fencing around the new inclusive playground.

7 to 28 February 2017.

Sections of the playground will be fenced off and out of bounds during installation of the fencing. Play equipment will still be open to the public.

Additional information and photos can be found on the Corrigans Reserve inclusive playground project page.

Contact: Carl Ginger, Project Engineer

Phone: 0437 447 881

Batemans Bay, Peninsula Drive

Installing subsoil drainage on the southern side of Peninsula Drive, from west of Lord Place through to Lincoln Crescent. 

27 February to 17 March 2017.

The road will be open at all times but short delays may be experienced during the installation of the drainage line across the road. Traffic control will be in place. Minimal works will take place during school bus hours.

Contact: Ian McGrath, Construction Coordinator

Phone: 0408 697 232

Batemans Bay Streetscaping Stage 2

Stage 2 of the streetscaping works, including footpath repaving, will be taking place along Orient Street from Beach Road to North Street.

20 February to 7 April 2017.

These works include replacement of kerb and gutter and repaving of the footpath, starting from the intersection with Beach Road. We will also be landscaping, installing new street trees with fairy lights, groundcovers and decorative totems.

Works may also be performed on weekends, early mornings and at night, and access to sections of footpath will be restricted while works are underway.  Lane closures will likely cause traffic delays and loss of parking spaces in Orient Street.

Additional information can be found on the Batemans Bay Streetscape project page.

Contact: Ross Garner, Project Engineer

Phone: 0427 733 469

Bodalla, Tyrone Bridge

Replacing the existing timber bridge with a 86m single lane concrete bridge.

August 2016 to Financial Year 2017-18.

Tyrone Bridge is on Nerrigundah Mountain Road just west of the intersection with Eurobodalla Road, approximately 9km west of Bodalla.

Additional information can be found on the Tyrone Bridge replacement project page.

Contact: Carl Ginger, Project Engineer

Phone: 0437 447 881

Long Beach, Cullendulla Drive

Reconstructing and widening the shoulder of Cullendulla Drive from from the intersection with Kettle Road to the turn south into Blairs Road.

1 February to 14 April 2017.

Works also include overlaying to improve the current road surface and installation of safety barriers.

Traffic control will be in place from time to time and residents and road users should expect delays.

Contact: Ian McGrath, Construction Coordinator

Phone: 0408 697 232

Tuross Head, Coila Avenue

Upgrading the stormwater system on Coila Avenue in Tuross Head.

20 to 24 February 2017.

Works include the replacement of approximately 60 metres of 375mm stormwater pipe and the construction of two new stormwater pits as part of a number of minor stormwater upgrades in the area of Anderson Avenue in Tuross Head.

Contact: Zac McAnally, Works Supervisor

Phone: 0427 409 018

Tuross Head, Marlin Street

Upgrading the road surface on Marlin Street in Tuross Head between Island View Road and Evans Street.

27 February to 10 March 2017.

Works include upgrade to approximately 90 metres of road pavement as well as a section of kerb and gutter as part of our road rehabilitation program.

Traffic control will be in place on Marlin Street between Island View Road and Evans Street from 7am to 4pm Monday to Friday.

Contact: Craig Hibel, Works Supervisor

Phone: 0407 065 889

Nerrigundah, Cadgee Bridge

Replacing the old three span timber bridge with a concrete structure.

October 2016 to March 2017.

Cadgee Bridge is on Eurobodalla Road crossing Gulph Creek downstream from Nerrigundah village. It was washed away in the floods of January 2016

Additional information can be found on the Cadgee Bridge replacement project page.

Contact: Carl Ginger, Project Engineer

Phone: 0437 447 881

Sunshine Bay, Caseys Beach

Upgrading the rock seawall at the southern end of Caseys Beach, from the bridge to the sewage pumping station. 

7 February to June 2017.

The seawall upgrade will also include construction of a set of concrete stairs from the car park to the beach. Conditions permitting, works may also take place on Saturdays between 7am and 2pm.

Additional information can be found on the Caseys Beach seawall upgrade project page.

Contact: Richard Dixon, Water and Sewer Technical Officer

Phone: 0438 038 701