Current works

Completion timeframes of current works are subject to weather conditions.

We will make every effort to minimise disruptions to traffic, parking and pedestrians during work times.

To help work run as smoothly as possible, we ask pedestrians and motorists to follow any signage and traffic control measures.

Shire-wide, bridges

What: Repairing or rebuilding bridges affected by bushfire and floods.

Some bridges will be repaired or replaced with timber while others are being rebuilt using concrete.

Why: To provide safe access to all communities.

When: January 2020 until works are complete

More info: Restoring bridges

Contact: Moruya Depot, 4474 1391

Shire-wide, rural roads

What: Maintenance grading and gravel re-sheeting various unsealed roads in the shire.

Traffic control measures will be in place and commuters may experience short delays.

Why: To maintain the roads to a reasonable level.

When: From July 2020 to June 2021

More info: Grading schedule

Contact: Moruya Depot, 4474 1391

Shire-wide, weed spraying

What: Spraying urban and rural roadsides, including the Kings Highway, to control the growth of woody weeds, shrubs and trees.

Metsulfuron (Brush-Off) and Glyphosate (Roundup) will be used.

Why: The spraying will reduce hazards caused by tree and shrub growth and help protect road pavements from tree root damage.

Commuters are asked to take care around slow-moving spraying vehicles.

When: November to December 2020, weather permitting.

Contact: Moruya Depot, 4474 1391

Batemans Bay, Beach Road

What: Rebuilding the road and pathways between Club Catalina and Batemans Bay Marina.

The project also involves replacing stormwater infrastructure, water mains, kerb and gutter and extending the concrete median.

Traffic control will be in place and commuters should allow extra time to travel through the area.

Why: To improve safety and adapt to sea level rise.

When: February to December 2020, weather permitting

More info: Beach Road safety upgrade

Contact: Moruya Depot, 4474 1391

Belowra, Belowra Road

What: Rebuilding Belowra Bridge.

The temporary side access track will remain open during works.

Why: To restore permanent access and increase resilience.

More info: Restoring access - Belowra Valley bridges

Contact: Moruya Depot, 4474 1391

Broulee, Captain Oldrey Reserve

What: Constructing a new sewage pumping station and rising main.

The rising main will be installed through Captain Oldrey Reserve and to the new pump station site in on private property to the west.

Reserve users can expect increased vehicle movements. Interruption to local sporting activities is not expected.

Why: To allow for development and transport sewage to the Tomakin Sewage Treatment Plant.

When: March 2020 to July 2021, weather permitting

Contact: Brent Parker, Water and Sewer Engineer, 4474 1000

Deua River Valley, Araluen Road

What: Stabilising the roadside slopes at various locations along the road.

The road is closed to through traffic and commuters may experience long delays for up to a few hours.

Why: To restore the batters damaged during the July and August floods. Loose material will be removed to re-establish stable roadsides.

When: October 2020 until work is complete

Contact: Moruya Depot, 4474 1391

Deua River Valley, Araluen Road - Bradburys Bridge

What: Rebuilding Bradburys Bridge.

The road will be impassable for the duration of works.

Why: To restore permanent access and improve resilience.

More info: Restoring access - northern bridges

Contact: Moruya Depot, 4474 1391

Eurobodalla, Eurobodalla Road

What: Rebuilding Reedy Creek and Peach Tree bridges.

The temporary side access tracks will remain open during works.

Why: To restore permanent access and improve resilience.

More info: Restoring access - Eurobodalla Valley bridges

When: November to December 2020

Contact: Moruya Depot, 4474 1391

Guerilla Bay, Burrewarra Point

What: Building a viewing platform.

Why: To improve safety, protect the environment and enhance low impact activities.

This is an identified action in Recreation and Open Space Strategy 2018

When: September to December 2020

Contact: Facilities Management Coordinator, Chris Tague, 4474 1325

Malua Bay, Mulgowrie Street

What: Rebuilding a section of the road.

New stormwater drainage, kerb, gutter and road surface will be installed.

Residents and visitors will be able to access properties but the road will be closed to through traffic during works.

Why: To improve and maintain the road network.

When: August to December 2020

Contact: Moruya Depot, 4474 1391

Merricumbene, Araluen Road

What: Stabilising the roadside slopes at various locations along the road.

The road is closed to through traffic and commuters may experience long delays for up to a few hours.

Why: To restore the batters damaged during the July and August floods. Loose material will be removed to re-establish stable roadsides.

When: October 2020 until work is complete

Contact: Moruya Depot, 4474 1391

Mogendoura, Larrys Mountain Road

What: Building a new bridge alongside Codys Bridge.

Codys Bridge will remain open during works.

Why: To maintain access and improve resilience.

When: November 2020

Contact: Moruya Depot, 4474 1391

Mogo, Annett Street

What: Rebuilding a section of the road.

New stormwater drainage, kerb, gutter and road surface will be installed.

The road will be closed to through traffic during works. Pedestrians access will be maintained.

Why: To improve and maintain the road network.

When: October to December 2020

Contact: Moruya Depot, 4474 1391

Moruya, George Bass Drive

What: Building a new access road to service the airport.

The road will operating under traffic control and commuters should allow extra time to travel through the area.

Why: To provide access to the new western subdivision.

More info: Moruya Airport upgrade

When: September to December 2020

Contact: Moruya Depot, 4474 1391

Moruya, Gundary Oval

What: Providing new amenities building.

Why: To improve player comfort. The work is a priority action identified in the Recreation and Open Space Strategy 2018.

When: August 2020 to February 2021

Contact: Facilities Management Coordinator, Chris Tague, 4474 1325

Moruya, South Head Road

What: Widening a section of the road, patchng the pavement and levelling the side of the road.

The area on the southern side of the road between Keightley Street and Congo Road is being prepared for the next section of shared pathway.

Traffic control measures will be in place and commuters should expect delays.

Individual residents will be notified if access to properties will be affected.

Why: To improve safety for motorists, pedestrians and cyclists.

When: December 2020, weather permitting.

Contact: Moruya Depot, 4474 1391

Narooma, Bill Smyth Oval

What: Improving field lighting, extending the amenities building and resurfacing the tennis courts.

Why: To improve playability, player comfort and privacy.

When: Lighting and amenities (October to December 2020), tennis courts (9 to 22 November 2020)

Contact: Facilities Management Coordinator, Chris Tague , 4474 1325

Nerrigundah, Gulph Creek Bridge

What: Rebuilding the bridge damaged by bushfire.

Nerrigundah Mountain Road will be closed while the old bridge is demolished and the new bridge is built.

Why: To increase resilience of our bridges.

When: July to October 2020

More info: Restoring access - Eurobodalla Valley bridges

Contact: Moruya Depot, 4474 1391

Potato Point, Potato Point Road

What: Constructing a sewage pump station, sewer rising main and water main.

Commuters should expect heavy machinery to be active along the road.

Why: To provide reticulated sewage infrastructure for Potato Point significantly reducing the risk of harm to the environment and public health.

More info: Potato Point sewerage Scheme

When: October 2020 - August 2021

Contact: Moruya Depot, 4474 1391

Sunshine Bay, Caseys Beach

What: Upgrading the Sewage Pumping Station (SPS) in Sunshine Bay at the southern end of Caseys Beach.

Access to the car park will be limited and the public toilets will be closed.

Why: To ensure greater reliability of the local sewerage infrastructure.

When: July 2020 to February 2021

Contact: Water and Sewer Engineer, Brent Parker, 4474 7409

Tomakin, Tomakin Road

What: Upgrading a 1.4km section of the road east of Dunns Creek Road.

Why: To improve road safety, drainage and property access.

The road will operating under traffic control and commuters should allow extra time to travel through the area.

When: September to December 2020, weather permitting.

More info: Tomakin Road safety upgrade

Contact: Moruya Depot, 4474 1391