Beach Road, Batemans Bay CBD Upgrade

Project: Upgrading of Beach Road from the intersection with Vesper Street (Princes Highway) to Orient Street in Batemans Bay CBD.

Cost: $3 million funded by the Australian Government's Building Our Future program.

Timeframe: June 2018 to December 2019.

Details

The major improvement will provide significant benefit to the community by improving road safety and road network capacity as well as reducing traffic congestion and travel times. The project includes:

  • an additional right-turn lane on Beach Road for eastbound traffic at Orient Street to address road safety and provide capacity for right-turn vehicles
  • an additional left-turn lane out of Beach Road onto the Princes Highway to provide additional capacity for left-turn, through traffic to Mackay Park and right-turn traffic
  • provision of dual lanes exiting Mackay Park onto the Princes Highway to increase capacity from the Mackay Park precinct
  • additional capacity at the existing Perry Street north leg of the Beach Road roundabout
  • new medians and pathways on Beach Road with pedestrian control measures and refuges to improve pedestrian safety.

The Beach Road overview plan shows locations of additional traffic lanes and footpaths

Latest News

June  2019

  • Stormwater drainage pipe works are now complete along Beach Road between Orient and Perry streets.

The retaining wall under construction has a wood grain look.

  • Our crews will now prepare the same stretch for a new footpath, landscaping and a retaining wall using wood grain concrete sleepers purchased from Cameron’s H Hardware. The work will incorporate replacement of the path linking Beach Road to Bent Street.

May 2019

  • A Council crew has been working on a new footpath alongside Hill Street to provide a link between the northern end of Bent Street and Mackay Park.
  • This pathway is identified as a priority in the Eurobodalla Pathway Strategy 2017 and is funded through the NSW DPI Stronger Country Communities program.
  • Crews have now resumed work on the southern side of Beach Road between Orient and Perry streets installing stormwater pits and pipes streets before landscaping the area.

April 2019

  • Construction crews have returned to site to start on a new pathway linking the Hill Street footpath near McDonalds to the northern end of Bent Street. The concrete path will include stepped sections.
  • After the April school holidays crews will focus on works along Beach Road.
  • A new pathway and retaining wall will be built on the southern side of Beach Road between Commercial Lane and the Perry Street roundabout.

February 2019

  • Our water team has been upgrading the water infrastructure while construction works are on hold.
  • An old water main is being replaced on Beach Road between Orient Street and the Perry Street roundabout.
  • A new water main is going in along Perry Street to increase the water capacity to the CBD.

January 2019

  • The new lanes are operating well assisting the flow of traffic through Batemans Bay.
  • Construction crews will return to site after Easter to complete the project.

December 2018

  • Traffic light sensors have been installed at all four approaches to the Beach Road and Princes Highway intersection.
  • A pedestrian fence has been erected on the new centre concrete median on Beach Road between the Princes Highway and Perry Street.
  • The new pathway has been extended and turf has been laid outside the Visitor Information Centre.
  • After a tidy up of the site on 14 December, work ceased to avoid disruption to Christmas shoppers and commuters.
  • Crews will be back on site in 2019 after the busy summer period.

Late November 2018

  • Beach Road was closed for a night to allow works to be undertaken with minimal disruption to commuters and pedestrians.
  • The traffic lights at the Princes Highway intersection have been moved to cater for the newly widened road.
  • The lights are operating as usual and pedestrians can access all corners.
  • The new left turn lane has been sealed, temporary line marking applied and opened to traffic.
  • Crews are now working on the centre concrete median between the Princes Highway and Perry Street.

Early November 2018

  • Crews are gearing up to seal the new left turn lane on Beach Road later in the month.
  • The traffic lights at the intersection of Beach Road and the Princes Highway will soon be moved to suit the newly widened road.

  • The footpath along the southern side of Beach Road adjacent to the Visitor Centre is now finished with adjoining kerb and gutter installed and looking smart.
  • Electrical crews have been installing new street lighting to shine on the Princes Highway intersection.

  • Meanwhile, further east along Beach Road between Orient and Perry streets, the retaining wall has been dismantled to increase the road width and allow for a new pathway.

October 2018

  • Although the rain has been very welcome it did affect our scheduled temporary road closure. Beach Road was closed between the Princes Highway and Perry Street for a couple of nights to enable works to be completed with only minimal disruption to traffic.
  • We have started works at the eastern end of Beach Road (pictured above left), preparing for the new footpath.
  • The newly created extra lane (above right) on Beach Road will be sealed in November.
  • Soon the street lights and traffic signals will be moved to their new locations to fit in with the widened road.

September 2018

  • The footpath is being built and kerb and gutter has been installed defining the edge of Beach Road.
  • Works continue alongside the Batemans Bay Visitor Information Centre to widen Beach Road.
  • Water mains have been upgraded and relocated.
  • Preparation works are underway to shift the highway intersection traffic lights to suit the wider road.

August 2018

  • Excavation has begun alongside the Batemans Bay Visitor Information Centre to make way for the new pavement that will form the additional left hand turn lane onto the Princes Highway.
  • Electrical infrastructure is being upgraded and power poles and cables are being relocated to make way for the road widening.
  • Our Water Services team have been upgrading the water mains and relocating pipes underneath the new footpath.

June & July 2018

  • Preliminary works began involving tree removal along Beach Road to allow for road widening and installation of a new water main, underground telecommunications and overhead power lines.
  • The Visitor Information Centre car park has been modified to cater for the widening of Beach Road. Access to the car park remain via the Beach Road/Perry Street roundabout.

More Information

For more information about this project, please contact Lewis Oldfield, Project Engineer: