Current works

Council carries out work across Eurobodalla to build and improve local roads and infrastructure.

Batehaven, Caseys Beach+

We’re rebuilding the seawall between Beach Road and Caseys Beach.

Why: To protect Beach Road from coastal erosion, storm damage and large waves washing over the wall.

When: August 2026 to July 2027

Work includes:

  • rebuilding the seawall using layers of hard-wearing rock
  • replacing the two sets of beach stairs once the seawall work is finished

Impacts during work:

  • The two sets of stairs within the work area will be closed during construction
  • Beach access is available via the northern car park and the stairs near the southern toilets.
  • Beach users will not be able to walk through active work areas which will move gradually along the beach as construction progresses.
  • Heavy vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • The parking and cycling lanes will not be available while work is underway.

Traffic impacts: Live Traffic NSW | Incident Details

More information: Batemans Bay coastal protection work

Cadgee, Wattlegrove Road+

We're upgrading the first section of the road.

Why: To allow for better flow of water in the creek, improve road surface and reduce maintenance requirements.

When: April to October 2026

Work includes:

  • removing the old culvert at the creek crossing
  • installing new culverts and headwalls
  • rebuilding the crossing, tying in both sides of the road
  • grading the road
  • restoring the area.

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters may experience delays.
  • Commuters will be diverted along a short side track  around the work area.

More information: Phone our construction team on 4474 1391.

Catalina, Ridge Street+

We're upgrading the water mains in a section of the street.

Why: To maintain and improve the local water supply.

When: September to October2026

Work includes:

  • installing new water pipes and service lines in the nature strips
  • connecting the new pipes and restoring the area.

Impacts during work:

  • Some sections of driveways may need to be temporarily removed to install the pipes. We’ll fully restore any affected driveways at the end of the project.
  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • If we need to interrupt water supply or property access, we’ll notify individual households.

More information: Phone our water team on 4474 1391

Kianga, Montague Avenue+

We're upgrading the water mains in a section of the street.

Why: To maintain and improve the local water supply.

When: August to October 2026

Work includes:

  • installing new water pipes and service lines in the nature strips
  • connecting the new pipes and restoring the area.

Impacts during work:

  • Some sections of driveways may need to be temporarily removed to install the pipes. We’ll fully restore any affected driveways at the end of the project.
  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • If we need to interrupt water supply or property access, we’ll notify individual households.

More information: Phone our water team on 4474 1391

Mogo, Princes Highway+

We're helping Transport for NSW to upgrade the area outside Mogo Public School.

Why: to improve pedestrian safety

When: August to October 2026

Work includes:

  • building a footpath, retaining wall and kerb and gutter
  • formalising the road shoulder for parking
  • installing a pedestrian safety fence

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.

More information: Phone the Transport for NSW project hotline on 1800 555 638

Moruya, Albert Street+

We're installing a raised pedestrian crossing near the Moruya High School entrance.

Why: To improve safety and access for students, staff and the wider community.

When: 28 September to 9 October 2026 (weather permitting)

Work includes:

  • constructing a raised pedestrian crossing near the school entrance
  • installing zebra crossing markings and signs
  • restoring the road following construction

Impacts during the work:

  • Albert Street will be closed at the worksite during construction
  • there will be no through access between either side of the work area
  • access to properties on both sides of the closure will be maintained
  • pedestrians access will be maintained
  • please allow extra travel time and follow traffic control directions
  • Live Traffic NSW

Once complete:

  • the crossing will operate at all times
  • motorists must give way to pedestrians using the crossing
  • the raised platform will improve pedestrian visibility, accessibility and encourage lower vehicle speeds near the school

More information: Phone our construction team on 4474 1391

Moruya, Bergalia Street+

We're building a roundabout at the Dwyers Creek Road intersection.

Why: To improve safety for our growing community. This upgrade will help make the area safer for motorists, cyclists and pedestrians by slowing traffic and reducing the risk of crashes.

When: August to November 2026

Work includes:

  • adjusting the road layout to accommodate the new roundabout
  • constructing the concrete roundabout and traffic islands
  • resurfacing the road
  • installing new signs and line marking
  • restoring the surrounding area once the work is complete.

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters may experience delays.

More information: Phone our construction team on 4474 1391.

Moruya, Lagoon and Murray streets+

We're upgrading the water mains in sections of the two streets.

Why: To maintain and improve the local water supply.

When: September to October 2026

Work includes:

  • installing new water pipes and service lines in the nature strips
  • connecting the new pipes and restoring the area.

Impacts during work:

  • Some sections of driveways may need to be temporarily removed to install the pipes. We’ll fully restore any affected driveways at the end of the project.
  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • If we need to interrupt water supply or property access, we’ll notify individual households.

More information: Phone our water team on 4474 1391

Moruya, Princes Highway+

We're building a roundabout and new roads alongside the TAFE and Essential Energy station.

Why: To provide access to future housing developments in Moruya, the new Eurobodalla Emergency Services Precinct, and the Moruya TAFE campus.

When: January to December 2026

Traffic impacts: Live Traffic NSW

More information: South Moruya roundabout

Narooma, Bar Beach+

We're installing a new shark net.

Why: to continue providing a designated swimming area at Bar Beach.

When: 25 September 2026

Work includes:

  • installing new buoys and connection points
  • placing the shark net in the water
  • securing the net to the new support piles

Impact during works:

  • machinery and work vehicles will operate on the beach
  • swimming and access to parts of the beach may be temporarily affected
  • please follow directions from workers and take extra care around the work area

More information: Phone our construction team on 4474 1391

Rosedale, Rosedale Parade+

We're upgrading the water mains in a section of the street.

Why: To maintain and improve the local water supply.

When: September to November 2026

Work includes:

  • installing new water pipes and service lines in the nature strips
  • connecting the new pipes and restoring the area.

Impacts during work:

  • Some sections of driveways may need to be temporarily removed to install the pipes.
  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • If we need to interrupt water supply or property access, we’ll notify individual households.

More information: Phone our water team on 4474 1391

Shire-wide, sealed roads+

We're maintaining sealed roads across the Eurobodalla by repairing potholes and carrying out heavy patching where needed.

Why: To improve safety and drivability by filling potholes as a quick repair, reducing the risk of vehicle damage and helping stop the road surface from getting worse. Where a longer-term fix is needed, we may carry out heavy patching to repair larger or more damaged sections of sealed road.

When: Work is ongoing

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • The road surface may be uneven or disturbed while pothole repairs and patching are underway, so drivers should slow down and take extra care.
  • Traffic control measures will be in place, and commuters may experience delays.

More information: Phone our maintenance team on 4474 1391.

Shire-wide, unsealed roads+

We're maintenance grading Moruya Reservoir Road, Donalds Creek Road, Mymossa Road, Wamban Road, Noggarula Drive, Beashells Lane, Bumbo Road and Horse Island Road.

Why: To improve safety and drivability by smoothing the surface, removing corrugations and potholes, and helping water drain away from the road.

When: August 2026, subject to weather and road conditions

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • The road surface will be disturbed and may be uneven while grading is underway, so drivers should slow down and take extra care.
  • Traffic control measures will be in place, and commuters may experience delays or temporary restricted access.

More information: Grading schedule 2026-27

Tuross Head, Brighton Street+

We’re rebuilding the upper half of the road and installing kerb and gutter.

Why: To improve road quality and safety, and direct excess stormwater out of the area.

When: August to October 2026

Work includes:

  • installing stormwater pipes
  • constructing kerb and gutter on both sides of the street
  • connecting driveways to the new kerb and restoring impacted driveways
  • rebuilding the road base and laying a new bitumen surface
  • restoring the site once work is complete.

Impacts during work:

  • Large vehicles and equipment will operate in the area.
  • Traffic control measures will be in place, and commuters should allow extra travel time.
  • The site supervisor will contact individual households if property access will be affected.

More information: Phone our construction team on 4474 1391

More information

For more information about current works, please contact the Moruya Depot:

  • T: 02 4474 1391