Malua Bay roundabout

Project: Construction of a roundabout at the George Bass Drive, Sylvan Street and Kuppa Avenue intersection.

Timeframe: January 2024 to December 2025

Status: In progress

Cost and funding: $3.3 million under the NSW Government’s Fixing Country Roads program

Page last updated: October 2025

Latest news: October 2025

The first two layers of asphalt are down, creating a smooth and solid road surface. Just one more layer to go, and we’ll be all finished before you know it. If you're driving through the area, please take extra care and allow extra travel time.

Project details

We are working to:

  • design and build a four-leg roundabout at the intersection of George Bass Drive, Sylvan Street and Kuppa Avenue
  • include islands and paths within the roundabout to assist pedestrians and cyclists crossing the roads
  • install kerb and gutter and stormwater drainage
  • improve lighting of the intersection.

Benefits to the community:

  • improved road safety for motorists, cyclists and pedestrians
  • improved efficiency and accessibility for the transport network.

Environmental impacts:

We’ve prepared a Review of Environmental Factors to assess potential impacts related to the project's activities.

Plans:

We have prepared a plan for the roundabout.

Project updates

2025

  • In September, the roundabout took shape as the annulus was constructed and the first two layers of asphalt were laid.
  • Construction activities ramped up in August and traffic controllers managed traffic flow through the site.
  • The plans and assessments were finalised, ready to begin on-site work in mid-July.
  • We adjusted our plans to ensure no net loss of parking spaces.
  • Preparations began for relocating underground services to make way for the roundabout.

2024

  • We started preliminary work for the roundabout in December. This included upgrading the service lane along George Bass Drive.
  • Our design team worked on the detailed plan for the intersection.
  • We engaged specialist contractors to work on the design for the lighting and service relocations.
  • We began initial environmental and heritage assessments of the site.

2023

  • We were awarded funding for the project under the Fixing Country Roads program in October.

More information

For more information, please contact our Division Manager Major Projects, Phil Oste: